RUDA Reports 70.6% Completion of Chahar Bagh Project

RUDA Reports 70.6% Completion of Chahar Bagh Project

Lahore: Significant progress has been made on the Chahar Bagh development project, according to an update by the Ravi Urban Development Authority (RUDA) shared via their official Facebook page on August 23. The construction is moving swiftly toward completion, and many major milestones have been achieved.

As per the latest update, the earthwork, a crucial foundation of the project, is nearly finished, with 99% of the work completed. Additionally, the drainage system has been fully installed, ensuring efficient water management throughout the development. The sewerage system is also approaching completion, with 98% of the work finished. These achievements mark essential steps toward the completion of the overall infrastructure.

RUDA also reported that the construction of the boundary wall, an important security feature, has reached 92% completion. Meanwhile, overhead water tanks, which will provide a reliable water supply to future residents, have seen significant progress and are 82% complete.

Regarding the road infrastructure, the sub-base and base course works, vital for creating stable and durable roads, are at 69% completion. Water supply installations, a key component for ensuring the availability of clean water, are currently at 64% completion.

The Chahar Bagh project has achieved a remarkable 70.6% completion rate. The RUDA team continues to work diligently to meet its construction targets, ensuring the timely delivery of this ambitious project.

As the development nears its final stages, excitement is building for the future of Chahar Bagh, which promises to be a modern and well-planned urban community. The focus on infrastructure development ensures that the project will offer a comfortable living environment for its residents, with essential amenities like water supply, drainage, and sewerage systems in place.